top of page
Search

Three Estimates used by PERT

  • Writer: stid1103grp6
    stid1103grp6
  • May 16, 2018
  • 1 min read

Updated: May 17, 2018


PERT is a three point activity estimating technique that considers estimation uncertainty and risk by using three estimates to define an approximate probability for an activity’s cost or duration. The three estimates used are:


Most likely (M) - The cost/duration of the activity, based on a realistic effort assessment for the required work and any predicted expenses.

Optimistic(O) - The activity cost/duration based on an analysis of the best-case scenario for the activity.

Pessimistic(P) - The activity cost/duration based on an analysis of the worst-case scenario for the activity.



 
 
 

Comments


CONTACT

US

            stid1103grp6@gmail.com

               Universiti Utara Malaysia, 06010 Sintok, Kedah

bottom of page